Hello quick update,
we have run into an issue with the current building for our electrical needs and the cost to revamp the transformer exceeds the cost to just relocate the farm by many thousands in funds. We apologize but the next 2 weeks we will need a lobetter-suited suited office to get hashing again.
We have considered already and contacted several options and places. Giga-watt in Washington state, another hosting facility in Iowa state, as well as reaching out to local commercial building with 3 phase electric owners. Today we have a strong potential option for a new location (it becomes available January 1st), Bjorn is moving as quickly as he can to make the shift and deals.
Even though this adds time delays, it's because much of the world moves at a pace that we, in Blockchain, do not, IE: people are slower. To avoid a service interruption in the future, we will not lease after this first year, but will, in fact, build our own facilities for mining. The land for this has been secured ahead of time, so this is part of the good news.
Once we have our temporary location up and running then full plans for our own place, on our own property will be revealed.
Yours in business,
-The Janusproject Team